Download PDFNew York City’s annual infrastructure survey report estimated in 2020 that the maintenance costs of the Riverside Park Bridge W. 79th Street Traffic Circle would be $76 million. When the project went to bid just a few months later, the actual cost was almost double that, at $149.9 million.
- Sub title
- NYC’s Infrastructure Report Fails to Identify True Costs of Capital Projects
- Agency
- Subject
- Report type
- Reports - Other (Consultant/Staff)
- Date published
- 2024-03-15
- Language
- Fiscal year
- 2024