Audit Report on the Development and Implementation of the S-Elect Project by the New York City Board of Elections (7A06-111)

Downloadable Content

Download PDF

From an audit conducted on the Board of Elections, it was found that the Board successfully completed the S-Elect Project. The overall goals and requirements were met, but the Board needs to improve the project's security and implement a recovery plan. Recommendations have been made to address these issues.